In light steel stud partition wall construction, accurately calculating stud usage is a critical link for cost control and ensuring project schedules. This article systematically introduces the calculation rules, parameter values, and practical application methods for partition wall studs.

 

1. Calculation Preparation

1.1 Basic Data Measurement

Precisely measure the total length (L) and height (H) of the partition wall, with units uniformly in meters

Mark the positions and dimensions of door and window openings

Confirm the design-required stud spacing; when not clearly specified in design, use standard values

 

1.2 Key Parameter Determination

Vertical Stud Spacing: Typically 400mm or 600mm; recommended to reduce to 350mm in damp areas such as bathrooms

Horizontal Bracing Setup: Generally none when wall height ≤3m; 1-2 rows for 3-5m height; 3 rows for >5m height

 

2. Calculation Methods by Stud Type

 

2.1 Top and Bottom Tracks (Head and Floor Tracks)

As the top and bottom fixing components of the partition wall, the calculation formula is simplest:

Total Length = Partition Wall Length × 2 × 1.05

(The coefficient 1.05 represents a 5% waste allowance)

 

Empirical Coefficient: Regardless of vertical stud spacing, usage is approximately 1 meter/m²

 

2.2 Vertical Studs (Primary Structural Members)

These are the main load-bearing components of the partition wall, with two calculation methods:

 

Precise Calculation Method:

Number of Studs = (Partition Wall Length ÷ Spacing) + 1, rounded up

Total Length = Number of Studs × Partition Wall Height × 1.05


Example: For a wall 3m long, 2.5m high, with 0.6m spacing: Number of studs = 3÷0.6+1 = 6 studs, Total length = 6×2.5 = 15m


Empirical Coefficient Method (for quick estimation):

At 600mm spacing: 2 meters/m²

At 400mm spacing: 2.5 meters/m²

At 300mm spacing: 3 meters/m²

 

Optimized Algorithm for Large Areas (≥200m²):

 

Total Length = Partition Wall Length × Studs per Meter × Partition Wall Height × 1.05

 

Where "Studs per Meter" = 1÷Spacing + 1

2.3 Horizontal Bracing and Through-Runners

Through-Runners: 0.5m² for 1 row, 1m² for 2 rows

Horizontal Bracing: Only installed when height >3m or at gypsum board horizontal joints; calculation method same as vertical studs

 

3. Special Areas Treatment Rules

Door and Window Openings:

1. Deduction Principle: Vertical studs at opening positions should be deducted

2. Reinforcement Requirements: Add 1 additional vertical stud on each side of the opening

3. Above Door Opening: Main stud spacing should be adjusted to 200mm, with reinforcement studs added

 

4. Fittings and Accessories Calculation

Accessory Name Usage Standard Remarks

Self-tapping Screws 1kg/100m² Specification M4×20 or M5×20

Expansion Bolts/Cement Nails 4 pieces/meter of wall For fixing top/bottom tracks

Support Clips 3 pieces/vertical stud For fixing through-runners

Aluminum Rivets 100 pieces/100m² For special connections

Welding Rods 0.25kg/100m² For welding stud connections

 

5. Waste and Allowance Reserves

Standard Waste Rate: Total usage × 1.05~1.10 (i.e., 5%-10% allowance)

 

Additional Considerations:

Irregular wall shapes increase by 20%-30%

Areas with dense piping require increased stud usage

Secondary stud connection loss 3% (standard 3m-long studs have effective use length of 2.92m)

 

6. Complete Calculation Example

Case: Calculate stud usage for a partition wall 5m long × 3m high (vertical stud spacing 600mm, with 1 row of through-runner)

 

1. Top and Bottom Tracks: 5m×2×1.05 = 10.5m

2. Vertical Studs:

   Number of studs = (5÷0.6)+1 = 9.3 → Round up to 10 studs

   Total length = 10×3m×1.05 = 31.5m

3. Through-Runner: 5m×1 row = 5m (or 0.5m/m²×15m² = 7.5m by coefficient method)

4. Accessories:

   Self-tapping Screws: 0.15kg

   Expansion Bolts: 20 pieces

   Support Clips: 10 studs×3 pieces = 30 pieces

 

Empirical Coefficient Verification: Area = 5×3 = 15m²

Vertical studs: 15m²×2m/m² = 30m (close to precise calculation of 31.5m)

Top/bottom tracks: 15m²×1m/m² = 15m (Note: Empirical coefficient method includes both sides)

 

7. Important Considerations

 

1. Design Priority: When design drawings exist, calculations must follow design requirements; spacing cannot be arbitrarily changed

2. Site Verification: Using architectural drawings directly may ignore wall deviation errors; field measurement is recommended

3. Specification Matching: Different stud models have different load-bearing capacities; specifications must be unified in calculations

4. Quota Adjustments: When actual practice differs from quota sub-items in stud spacing or specifications, usage should be adjusted according to actual conditions

 

By systematically mastering the above calculation methods, you can ensure accurate stud usage and avoid material waste or shortages. For complex projects, it is recommended to use professional software or consult a cost engineer for verification.

 

Reference Note: The calculation methods in this article are integrated from standard practices in Decoration Engineering Quotas and Budgets and industry practical experience. Actual application requires flexible adjustments based on project design documents and site conditions.